![]()
ELECTRICAL ASSESSMENT
FOR
PANIOLO HALE
At
Kaluakoi, Molokai, Hawaii
Prepared By:
MORIKAWA AND ASSOCIATES, LLC
PO Box 880280
Pukalani, Maui, Hawaii 96788
May 2006
EXISTING ELECTRICAL SYSTEM
The site is serviced through the Maui Electric Company at 7.2Y/12.47 KV through five service metering locations at 120/240 volts, single phase, three wire. The metering
arrangements and quantities are broken down as follows:
| Meter Locations | Residential | Common Area |
| 1 | 16 | 1 |
| 2 | 15 | 1 |
| 3 | 16 | 1 |
| 4 | 16 | 1 |
| 5 | 15 | 1 |
The Common Area meters are on the Commercial metering rate “G” while the
Residential Metering is on the rate “R”.The Commercial Meters use a Circle A-W Company meter socket that has test by-pass
facilities, in compliance with Maui Electric Company Requirement.The Residential Meters use General Electric Meter Mod II, Catalog TMP36412R, in a
three or four vertical meter stack. This type of metering arrangement is still beingmanufactured by General Electric, although this model is available in parts only.
The present meters were noted to be mounted at approximately 16 inches. The meters are
mounted in non-compliance to Maui Electric Company’s current standard metercenterline mounting height of 3 feet minimum to a maximum of 6’-6”.
Maui Electric Company acquired the Molokai Electric Company along with its assets.
This includes the equipment installation at Paniolo Hale. Any future work involving the
replacement of the non-standard installation will need to comply with the currentstandards in effect at that time.
ASSESSMENT OBJECTIVES
As a part of this project, a review of the installed equipment was conducted on April 28,
2006 at the site with Mr. Bill King and Mr. Roland Zeitier and the Maui Electric Company Trouble Personnel.The intent was to observe and inspect, as much as could be visible, the electrical system
components, main and feeder breakers, wiring, termination lugs, grounding, enclosurecondition and prepare a recommended course of action.
OBSERVATIONS AND FINDINGS
Each of the five metering centers were observed for visible signs of corrosion, electrical
code conformance, electrical utility compliance, and system integrity. The following area recap of the findings:
1. Water entry into the metering enclosure is the primary cause of interior corrosion.
This was primarily due to water entry through the feeder raceways where ahandhole was installed at an elevation higher than the metering equipment. These
were observed at Metering Centers 1 and 2. Restricting water entry is essentialfor extending the equipment life.
2. Aluminum plated lugs and terminations have show signs of oxidation. Once a
break in the plating has occurred, oxidation adds electrical resistance to theconnection causing failure. In a few cases, an antioxidant compound was added
to the terminations. This material is not an electrical conductor and should beused per the manufacturer’s recommendations.
3. Limited exterior corrosion was observed on the metering enclosures. The house
panels at HP3, HP4 and HP5 showed signs of heavier corrosion. These unitsshould be replaced.
4. The main disconnect for the metering center has a metal channel to divert any
water from entering the breakers. This metal channel showed signs of corrosionthat allowed water to enter the main breaker. This was most evident at Meter
Center 3. Replacing this metal channel and applying a silicone sealant at alllocations will extend the breaker life.
5. The Maui Electric transformers at Meter Centers 1 and 2 showed signs of
corrosion. The unit at Meter Center 2 also was leaking oil (it is our understandingthat this transformer was replaced).
RECOMMENDATIONS
The following are recommendations for corrective action:
1. Perform preventive maintenance on the electrical metering enclosures. Because
these installations are “grandfathered” by Maui Electric, replace is necessary ifthe equipment is replaced. This preventive maintenance includes but not limited
to:A. Replacing all aluminum lugs with brass or copper lugs. Cleaning the
conductors, treating the termination with an antioxidant is okay, andproperly torque the new termination per manufacturer’s specifications, are
necessary steps.B. Replace all ground lugs with brass or plated copper.
C. Replace the main breaker for Meter Center 3. This appears to have the
greater of water damage.D. Repair the neutral bus at Meter Center 1. Check the condition of the
neutral bus at the other Meter Centers and repair as necessary.E. Thoroughly clean all the equipment interiors. Clean water can be used
with the electricity turned off but this need to be dried before closing thepanels or prior to painting.
F. Treat the rusted areas by cleaning, treating with zinc phosphate (Ospho or
JASCO are recognized trade names and can be available at most hardwarestores), and paint with a polyurethane type paint.
G. Clean, treat, and paint the metering enclosures. The color can match the
surroundings and does not need be gray in color.H. Seal any large openings (such as incorrectly placed knock-outs) with a
galvanized plate and stainless steel rivets. Treat and paint the plate toprevent rusting.
2. Prevent water entry into the electrical equipment. This consists of two
approaches, one externally and the other internally.A. Internally – prevent water entry through the conduit system from any
handhole that is higher in elevation than the metering equipment conduitentry.
Any water in the raceway should best be drained by the use of a shop-vac. After this is done, and the entry points cleared to prevent water entry, theconduit should be sealed with duct seal.
B. Externally – Building a roof to shelter the metering equipment from
falling rain will help increase the equipment life. These should not hinderthe utility meter reader’s ability from taking the readings however.
3. Prevent entry of vermin such as rats or mice. This is the reason for the use of
riveted metal plates to seal any of the larger holes. The use of foam will help butthis can be eaten away by vermin. We recommend all conduit entries be sealed
with duct seal, after being drained of water.
4. Investigate Maui Electric Company’s “Apartment House Collection
Arrangement” billing structure, where a 10% discount is applied to the electricalbilling (the minimum would not be less than the month meter charge) for single
point responsibility. The utility would continue to provide monthly meter readingbut the billing would be to a single responsible entity.
If this is a consideration, contact with Maui Electric Company could be made forany clarifications and contract preparation.
5. Attached are photos taken at each of the metering center locations for reference.
Incorporating the recommendations will assure extended life of the electrical serviceequipment. In the future, remote meter reading by Maui Electric will become a reality
which should revise the mounting height standards or even the type of meters used.